Sl No
Activities carried out in three years
Number
1
Total number of hamlets in ten villages.
54
2
Total number of hamlets has hamlet wise development plans.
50
3
Total number of Farmer Club.
42
4
Total number of water user associations.
29
5
Total amount of local contribution.
Rs. 25,08,623
6
Total number of Kisan Credit Cards.
143
7
Total number of new wells.
14
8
Total number of new community ponds.
13
9
Total number of wells renovated.
23
10
Total number of community ponds renovated.
8
11
Any other irrigation facilities (flow Irrigation)
2 Flow irrigations
12
Average water table at the start of the project.
18 feet
13
Average water table at the end of the project.
7 feet
14
Average distance from home to water source at the start of the project.
1.5  Km
15
Average distance from home to water source at the end of the project.
50-150  meters
16
Average water availability (how many months in a year) at the start of the project.
8 Months
17
Average water availability (how many months in a year) at the end of the project.
11 Months
18
How many farmers were involved in organic farming* at the start of the project? (*Organic farming is a form of agriculture that relies on techniques such as crop rotation, green manure, compost and biological pest control).
0
19
How many farmers are involved in organic farming at the end of the project?
626
20
How many farmers were involved in diversified farming system* at the start of the project? (*Diversified farming system is the practice of providing a variety of crops or animals, or both, on one farm).
0
21
How many farmers are involved in diversified farming system at the end of the project?
196 with Arhar & 177 with Maize
22
How many farmers were involved in SRI at the start of the project?
0
23
How many farmers are involved in SRI at the end of the project?
452
24
How many farmers were involved in SWI at the start of the project?
0
25
How many farmers are involved in SWI at the end of the project?
80
26
How many farmers had soil health cards at the start of the project?
0
27
How many farmers have soil health cards at the end of the project?
595
28
What are the major findings of the soil health testing?
Highly acidic due to huge imbalace application of Chemcial fertilizer
29
What action taken on the major findings?
Farmers applying Chuna (Lime) and Vermicompost
30
How many water testing carried out till date?
18 water bodies (1 hand pump, 1 Dari, 16 wells)
31
What are the major findings of the water testing?
Out of 18 wells only 1 hand pump well is drinkable and rest 18 is fully affected by Bacteria and not safe without treatment.
32
What action taken on the major findings?
Community using water only after boiling and bleaching power have been put.
33
Please define modern low cost farm technology.
Adoption of SRI, SWI, new agriculture equipments, Vermin compost, Azolla, diversified farming  & Nutritional Kitchen garden etc.
34
How many farmers were practicing this modern low cost farm technology at the start of the project?
0
35
How many farmers are practicing this modern low cost farm technology at the end of the project?
626
36
Rice (quantity) – average yield at the start of the project.
8 – 10 quintals in 1 acres of land
37
Rice (quantity) – average yield at the end of the project.
18 – 20 quintals in 1 acres of land
38
Rice (quality) – seed generation* of the plant at the start of the project. (*e.g. one rice grain produces a stalk yielding three grain, or 1:3).
Initially the Rice production was done traditionally in which tillering was 10 – 12 at maximum  per plant
39
Rice (quality) – seed generation of the plant at the end of the project.
Since the farmers adopted SRI system in which tillering is 40-60 per plant
40
Rice (stability of yield*) at the start of the project. (*able to withstand climatic variation).
In  traditional system it was lasting 6 months to 1 year
41
Rice (stability of yield) at the end of the project.
At the end of the project it was found 2 years
42
How many farmers were taking one crop in a year at the start of the project?
718
43
How many farmers are taking one crop in a year at the end of the project?
892
44
How many farmers were taking two crops in a year at the start of the project?
60
45
How many farmers are taking two crops in a year at the end of the project?
561
46
How many farmers were taking three or more crops in a year at the start of the project?
0
47
How many farmers are taking three or more crops in a year at the end of the project?
373
48
Farmers are taking what types of new corps now?
Vegetable (beans, French Beans, Cow pea, pumkin, bush type soybean, okra) Paddy, wheat, Arhar, Maize, Gram, Minor millets etc.
49
How many farmers were taking only one meal per day at the start of the project?
469 households
50
How many farmers were taking only two meals per day at the start of the project?
574 households
51
How many farmers were taking three or more meals per day at the start of the project?
124 households
52
How many farmers are taking only one meal per day at the end of the project?
0
53
How many farmers are taking two meals per day at the end of the project?
1111 Households
54
How many farmers are taking three or more meals per day at the end of the project?
855 Households
55
What types of food farmers were eating at the start of the project?
Rice, Sukti, Meat
56
What types of food farmers are eating at the end of the project?
Rice, Daal, Pulses, Vegetable (all kinds of seasonal vegetables), Meat, Fish, Poultry
57
How many months in a year farmers do not had food at the start of the project?
5
58
How many months in a year farmers do not have food at the end of the project?
0
59
Total number of vermin compost tank & vermi Beds in ten villages.
262 vermi Tanks + 452 vermi Beds
60
Total number of farmers using organic manure in their own field.
452
61
Total number of farmers is selling organic manure.
52
62
SHG –
a) total number of SHG,
40
b) total SHG members in all SHGs,
502
c) total savings in all SHGs,
Rs. 7,39,185
d) total loan issues till date in all SHGs,
Rs. 85,300
e) total loan recovered till date in all SHGs,
Rs. 38,300
f) total loan outstanding as on 24 June 2013 in all SHGs,
Rs. 78,000
g) interest rate,
5%
h) the purpose for loan taken,
Agriculture & Livestock
i) leadership of SHGs (M/F) and
120 (F)
k) Total SHGs with bank accounts.
21 SHG's
63
Total number of farmers with livestock.
209
64
Total number of farmers with income generation activity.
209
65
Total number of farmers with lac cultivation.  
869
66
Total number of panchayats with water management strategy.
3
67
Total households with ration cards.
477
68
Total households who have applied for ration cards?
634
69
Total number of women leadership at project level – farmer association, water user group, SHG, etc.
163
70
Total number of women leadership at panchayat level.
7
71
Changes in NSVK due to gender policy.
Due  to this staff level we promote gender staff and administration level as well as in Executive bodies
72
Total number of villages with the community based disaster risk mitigation strategies.
10
73
Action taken as per the community based disaster risk mitigation strategies.
Grain Bank, Seed Bank, Linkage with the forest department for tackle with wild animal, formation of 3 Mahasamuh
74
Name of government schemes accessed by community/project.
Social security scheme (PDS centre), Roads, wells, house, in Agriculture sector agriculture equipments ( Cono Weeder, sprayer, seeds, and organic fertilizer, RSBY, Janani Suraksha Yojna, MNREGA, NABARD linkage etc.
75
Total number of households benefited through each scheme.
Social security scheme (PDS centre): 265 families of 2 villages
Roads: 321 families of 3 villages
Irrigation cum Drinking wells: 21 HH
Indira Awas: 14 HH
Agriculture sector agriculture equipments (Cono Weeder, sprayer, seeds and organic fertilizer: 215 Farmers
Job under MNREGA : 234 Family
RSBY CARD : 204 Family
Janni Suraskha Yojna : 104 Family
NABARD linkage : 7 Farmers clubs
76
Total amount of government schemes accessed.
Rs. 68 Lakhs
77
Total number of villages with equitable water access strategies.
9 Villages
78
Total land under cultivation using organic farming at the start of the project.
0
79
Total land under cultivation using organic farming at the end of the project.
198.6  acres
80
Total land under cultivation using diversified farming system at the start of the project.
0
81
Total land under cultivation using diversified farming system at the end of the project.
120 acres
82
Average percentage of soil erosion at the start of the project.
80%
83
Average percentage of soil erosion at the end of the project.
30%
84
Average income of farmer at the start of the project.
24,000
85
Average income of farmer at the end of the project.
50,000
86
Total number of farmers using chemical fertiliser at the start of the project.
718
87
Total number of farmers using chemical fertiliser at the end of the project.
136
88
Total number of farmers with crop insurance at the start of the project.
0
89
Total number of farmers with crop insurance at the end of the project.
150
90
Public Distribution Shops available at each village at the start of the project.
2 PDS centre in 10 villages
91
Public Distribution Shops available at each village at the end of the project.
3 PDS centres in 10 villages
92
Major achievements of elected women leaders in panchayat in last three years.
Regular meeting of Gram Sabha, Awareness and access of Govt. Schemes,
93
Average migration at the start of the project.
80%
94
Average migration at the end of the project.
30%
95
Total number of training organised for Panchayat members during the project lifespan.
8
96
Training subjects.
Empowerment, roles  and responsibilities, and strategies to access Gov. Scheme, Role of Gram Sabha
97
Total percentage of women leaders at Panchayat level at the start of the project.
0
98
Total percentage of women leaders at Panchayat level at the end of the project.
60% (Out of 12 Members 7 are Women)
99
Total community contribution (year wise).
1st year Rs. 463599
2nd year Rs. 544727
3rd year Rs. 1500297
100
One case study. (Name of the beneficiary, Village name, Family information, Situation before support, Type of support and Situation after support).
Name of the beneficiary: Shiva Ram
Village name: Sundridih
Family information: Orphan boy married 2 years ago with the help of community. He lost his parents at the age of 14 years. Once he lost his parents he had to go through lot of difficulties. The community had great concern towards him therefore lot of moral supports rendered by the villages.
Situation before support: Meal taken only once a day and lacked knowledge of decent living style.
Type of support: Firstly appointed village point person in NSVK, a pair of pigletes accessed and training organaized.
Situation after support: Today is most successful in systematic livestock rising and Lac production. He sold livestock fare 40000 thousands recently yet has 8 piglets.
However, he sold Lac rupees of 80, 000 (eighty thousands rupees only) started saving in bank (After joining with the project he opened bank account) and bought 600 hundred kg's of fencing iron wire with the rupees of 26, 000 thousands. He is fencing his whole area and start systematic cultivation and livestock rising.
Moreover, taking 3 meals in a day, having bank balance, planning to plant Lac production plant, fishery, duckery and piggery in mass base.